The Building Sustainably Podcast · 2024-11-06 · 25 min
Key moments - from our scoring
Substance score
58 / 100
Five dimensions, 20 points each
The sequential test emerged from the 2007 floods and the Flood and Water Management Act, evolving through NPPF guidance (with significant updates in 2022-2023) to become a critical planning requirement. What began as a straightforward assessment of flood zones 1-3 has expanded to include surface water, groundwater, reservoir, and sewer flooding - creating significant complexity. The High Court cases involving Mead and Redrow have helped define what constitutes a "reasonably available alternative" site, with guidance suggesting a ±25% variance in site area or capacity is reasonable for comparison purposes. Chris and Jonathan stress that sequential testing requires genuine collaboration between flood risk engineers, drainage specialists, masterplanners, developers, and local planning authorities from the earliest stages. Material considerations beyond flood risk - such as grid connection requirements, ecological constraints, or areas of outstanding natural beauty - can legitimately steer development to higher-risk locations. Inconsistent interpretation across local authorities and ongoing NPPF reforms create ongoing ambiguity. The speakers emphasize that conducting rigorous sequential tests early, with clear project definition and agreed search areas, prevents costly judicial reviews and project delays later.
The sequential test steers development away from flood-risk areas by requiring developers to demonstrate their site is the most appropriate location considering flood risk. It has become contentious because post-2022 NPPF guidance expanded it from assessing only river and tidal flooding (flood zones) to include all flood sources - surface water, groundwater, reservoir, and sewer flooding - creating complexity particularly in areas designated as low-risk for river flooding but vulnerable to surface water flooding.
These High Court cases clarified that developers need not compare their site against every possible alternative location, and that a ±25% variance in site area or capacity represents a reasonable size band for comparison. The cases also established that developments cannot be artificially fragmented into smaller pieces to appear more flood-resilient if doing so loses essential elements like care facilities, public open space, or biodiversity gains that larger sites provide.
Beyond flood risk, legitimate material factors include grid connection proximity for energy schemes, ecological designations and areas of outstanding natural beauty that restrict development elsewhere, transportation routes, housing requirements, and site-specific constraints. If these factors limit where development can reasonably occur, higher flood-risk locations can be justified and approved.
Developers should assess whether a sequential test will likely be required before significant investment in master planning and site layout. Early engagement with the local planning authority to understand their track record with sequential tests, combined with defining the project's unique requirements upfront, prevents costly delays and potential judicial reviews if the test is not conducted until the appeal stage.
Ambiguity in NPPF guidance and associated policy practice guidance, combined with different levels of legal standing between the framework, guidance, and standing advice notes, leads local authorities to interpret and apply sequential test methodology differently. Recent DEFRA and Environment Agency guidance suggesting that allocated open space, biodiversity net gain, and public amenity areas may not require sequential testing represents ongoing evolution that has not yet been standardized in the NPPF.
Our reviewer’s read on each dimension, with quotes from the episode.
The episode provides solid, workable guidance on sequential testing with genuine practical value: the 25% ±threshold from case law, the need for disciplinary collaboration, the distinction between evaluating the whole red-line versus development-only parcels, and the emerging DEFRA guidance on open space exemptions. However, there is substantial filler - repetitive restatement of the ambiguity problem, vague throat-clearing about 'other material considerations,' and padding around the webinar reference. For a 25-minute episode on a technical topic, more concrete procedural detail and fewer circular discussions would improve density.
The red rose scheme, for instance, suggested that plus or, um, minus 25% of your site area or your site capacity, whether it's solar panels or battery storage or residential development, which is what it was in both these cases, that's a reasonable size band to compare your site with.
if your development has allocated areas of flood risk for open space, biodiversity net, gain public immunity, that is not built development that you may not need to do the sequential test.
The episode recycles well-known planning frameworks and standard case-law references (Mead and Redro) without meaningful reinterpretation. The core argument - that sequential testing has become ambiguous and requires multi-disciplinary collaboration - is not novel in planning circles. The practical wrinkles (red-line boundary segmentation, grid connection constraints, climate modeling challenges) are sensible but incremental rather than fresh thinking. No counterintuitive arguments or first-principles reconceptualization of when sequential testing should apply.
there's a lot of ambiguity and even in the decisions that are made, there's some ambiguity and some disagreement about those.
It's got to be a collaborative effort between the flood risk engineers, the drainage gu, the master planners, the client themselves.
Both guests have genuine operational credentials: Chris Patmore brings 30 years in flood risk and sustainable drainage plus expert witness testimony; Jonathan Morley has 17 years at RPS with direct involvement in sequential tests and high-risk developments, particularly energy infrastructure. Both are technical directors with hands-on case experience. However, they are consultant-practitioners speaking about their own firm's methodology rather than operators at client/developer level who faced these tests under deadline pressure. They represent supply-side expertise, not demand-side lived consequence.
I've been doing sort of flood risk and sustainable drainage for about 30 years. The idea of the sequential test has sort of come out of that do quite a bit of uh, expert witness on flood risk mainly and more recently on uh, sequential test.
I've been with the company about 17 years now and I've been involved in lots of flood risk assessments across the country and some international specialising in the energy and major infrastructure sector
The episode provides limited named examples and quantifiable data. The Mead and Redro court cases are named but not detailed. Two project examples are described (energy scheme with grid constraints, residential scheme with country park) but lack specifics: no site names, no dates, no figures on cost, timeline, or outcome metrics beyond 'approved' and 'under construction.' The 25% threshold and ±size band are numbers, but most other claims remain abstract: 'many occasions,' 'plenty of examples,' 'a number of sites.' For a technical episode, more project detail and fewer generalizations would ground the advice.
So it was two companies, Mead and Redro, that uh, were both put together to challenge one of the planning regulations
One of the overriding material considerations for that is proximity to the grid connection. So that was upfront and foremost the uh, driving factor that then defined our search area
The host (Emily McGee) asks open, agenda-setting questions but rarely probes or challenges. Questions are largely 'and then what?' rather than 'why' or 'but what if.' She does not push back on vague claims ('quite a lot,' 'many occasions'), does not ask for timeline or cost specifics, and does not test the guests' assertions against competing principles. The guests are allowed to repeat the 'ambiguity' framing without being asked whether that reflects genuine legal uncertainty or simply poor communication by authorities. Follow-ups are minimal; there is no productive disagreement or Socratic pressure.
So you mentioned previously about the nppf, so the National Planning Policy Framework. Are ah, there any requirements, updates or guidance on this that people can follow?
So with that sort of approach, with that, do we have any project example that either of you both have been through as part of that?
Computed from the transcript - who did the talking, and the words that came up most.
In this episode of The Building Sustainably Podcast, Chris Patmore and Jonathan Morley, Technical Directors at RPS, join Emily McGee to unpack the sequential testing in flood risk assessment. They discuss the evolution of sequential testing from the Flood and Water Management Act, its legal implications, and practical applications in flood risk management. Chris and Jonathan also share real-world case studies that highlight the importance of collaboration among engineers, planners, and local authorities. Chris is a Technical Director with over 30 years of experience specialising in flood risk and sustainable drainage design for major infrastructure projects. His expertise spans residential development, rail, highways, petrochemical, and energy installations. Chris has experience in traffic studies, feasibility design, and environmental analysis of hydrology and traffic, particularly in performing NPPF sequential test analysis in collaboration with project planners. Jonathan is an experienced project manager and hydrology expert who has authored numerous Environmental Impact Assessments (EIAs), Flood Risk Assessments (FRAs), and Surface Water Management Plans.
Transcribed and scored by The B2B Podcast Index.
Speaker A: Foreign.
Speaker B: Welcome to the Building Sustainably podcast by rps. Sustainable resilient development demands a new approach to how we plan, design and build. We invite you to join us as we explore real life case studies and offer practical guidance. Here's your host, Emily McGee.
Speaker A: Welcome to today's episode in the Building Sustainably podcast series. Today's topic is hydrology Sequential test essentials. I'm here today with Chris Patmore and Jonathan Morley. Welcome both. We'll start with introduction.
Speaker C: So Chris, I'm a technical director at rps, joined earlier this year. I've been doing sort of flood risk and sustainable drainage for about 30 years. The idea of the sequential test has sort of come out of that do quite a bit of uh, expert witness on flood risk mainly and more recently on uh, sequential test.
Speaker D: Hi, I'm Johnson Morley, I'm also a technical director with RPS. I've been with the company about 17 years now and I've been involved in lots of flood risk assessments across the country and some international specialising in the energy and major infrastructure sector of which we have been party to some sequential tests, um, and being involved in some high risk developments.
Speaker A: Fantastic. Thank you both for joining today as well. So I think it's best to start with what is sequential testing or the sequential test?
Speaker C: Yeah, so I think just sort of even have to say, sort of go back a little bit and start with you know, the flood risk concept, uh, in general. And the flooding in 2007 resulted in the Flood and Water Management act, which then resulted in a lot of legislation being passed and was also fed back into the MPPF planning guidance. And it's out of the MPPF that the sequential test evolved as a way of steering development away from areas of flood risk. And over the years that has evolved to be a bit more specific. Whereas originally it was based on the flood maps for planning, which is flood zone 1, 2 and 3. Now it's more defined as any form of flood risk. And that's really where it's come to its fore at the moment and why we're probably talking about it today.
Speaker A: So you mentioned previously about the nppf, so the National Planning Policy Framework. Are ah, there any requirements, updates or guidance on this that people can follow?
Speaker C: There's actually always updates and the last update, the main update that we reference is the 2023 update, the MPPF. But it was really sort of 2022 that the idea of all sources of flooding came in, which has really kicked off a sort of a debate about how far do you go with a sequential Test and who deals with it. And that's really where we're at and has caused a lot of confusion.
Speaker A: So that's why we've got this sequential test as the hot topic at the moment and with the increased sort of scrutiny or legal challenges that we've got.
Speaker C: Absolutely. So one of the things is that the sequential test is, as I mentioned, to try and steer development away from areas of flood risk. So initially it was defined as flood zone one, which is sort of areas of the country with low or little fluvial or tidal flood risk. But now it also includes surface water flood risk, it includes reservoir flood risk, groundwater, uh, sewer flooding, all sources of flood risk. The main reason it's become a hot topic is primarily around surface water. Cause there are parts of the country where a site is in flood zone one, but if you take into account sources of surface water, then it becomes a very different beast and the site can be quite heavily impacted by surface water flood risk.
Speaker D: As I say, I think one of the challenges has been over the years is the ambiguity within the legislation and the guidance. So historically, as Chris mentioned, there was a sort of focus on flood zones, which would be the river flooding and tidal flooding. However, that has in a couple of years been applied to all areas of flooding, which was then, as Chris mentioned, strengthened within the mppf. But as there was some lingering ambiguity that has led to, as you mentioned, Emily, some legal challenges and, um, being progressed through the courts, which has sought to deal with some of that ambiguity, but in some areas hasn't quite cleared it up.
Speaker A: So with that in terms of the legalities and with sort of linking to case law examples like that, do you have any case lawyer identifiers that you can relate to? I know that you previously mentioned the reasoning why it's come about, but any other decisions that can relate to the sequential test?
Speaker C: Yes, I think as Jonathan said, there's a lot of ambiguity and even in the decisions that are made, there's some ambiguity and some disagreement about those. There's two cases that were brought together that made it all the way to the High Court where the sequential test was being tested. So it was two companies, Mead and Redro, that uh, were both put together to challenge one of the planning regulations, but it encompassed sequential test. And there was a lot of questions about, uh, things such as what is a reasonably available alternative? And also things like do you consider every single site? Can you break your development up into little parcels? There are all less flood risk. Is that the same as your original plan? Are there elements of your scheme that can only be achieved in the hold. And if you take them apart, you lose that integrity. And so all of those kind of debates are taken through in the case law and the general consensus seems to be moving towards, you do have to take a reasonable test that your site has particular elements to it that you can't provide by breaking it up into very, very small pieces. So there's a limit. So the red rose scheme, for instance, suggested that plus or, um, minus 25% of your site area or your site capacity, whether it's solar panels or battery storage or residential development, which is what it was in both these cases, that's a reasonable size band to compare your site with. But if you fragment it into like 10% of your site, are you providing all of the other stuff that you might be providing, like care centers or public open space, biodiversity net gain, maybe even a school site that all the bigger sites can provide that the smaller ones can't? So it's helped to try and hone in on those particulars about your site. That means that you don't have to compare it with every single dwelling, extension or a little bit of infrastructure.
Speaker A: And then you've obviously spoken about the challenge of the ambiguity and we've gone through this definition and path within discussion, case law that's also associated. But what is the practical application with it?
Speaker C: So certainly the way that we're approaching it, it's got to be a team effort, um, because it can't be done by say, a flood risk guy on their own or a planner, necessarily on their own, or a client wanting to do the whole thing on their own. It's got to be a collaborative effort between the flood risk engineers, the drainage gu, the master planners, the client themselves. But even beyond that, there's a collaboration required between the client team, the developer and the local planning authority, because ultimately they've got to agree that you are assessing what you're assessing against a reasonable database, if it were, and things like the local plan. And certainly I think a lot of people know that at the moment, local plans are sort of all over the place at the moment, that there are draft local plans, then there are adopted local plans, and there are local plans that have just started all of those things. So there's data in there, but it's, it's getting hold of it and making sure that you are comparing, you know, eggs with eggs, et cetera. It's the collaboration that really needs to help right from the start. So we usually work with planners to define the search areas and then Feed that back to the local planning authority to agree that we're looking at the right area, the right type of development and that we're not. Although we are excluding other types of development which uh, would be unnecessary to assess and try and get that collaborative thing up front.
Speaker D: One of the other touching on one of Chris's points is other material considerations as well. So there may be other material factors beyond flood risk which steer a development to a specific location. So there may be areas of outstanding natural beauty that prohibit development in that location. There may be ecological factors or alternatives such as road transport routes or housing requirements, et cetera, that may limit where that search area is or those reasonably available sites. Some of those sites may be discredited due to those other material factors which then locates a potential development at an area of higher risk than you would prefer to have.
Speaker C: So I think it's back to it's not just a hydrological uh, site location that the MPF may suggest that it is. There are other factors that we've got to work in parallel. And you know, other examples are grid connectors and various other things. They really need to be near the grid. Locating them in a completely different area and having to have a grid connecting or a connection point that's 10, 20 km is not engineeringly the best sustainable solution. So getting that definition of the project right up at the beginning and agreeing that helps to define and it does smooth out the psychiatry test process.
Speaker D: And I think as Chris mentioned as well, we've assisted on clients which have actually been subject to legal challenge, um, where an application has gone through judicial review requiring a sequential test. An inadequate sequential test would hinder development and impact on developers program as well as development costs. Because you're just continually having to go through the JR in order to facilitate the development kicks into long grass and costs developers significant amount of money and impacts on the investment long term profile. So it is best to undertake um, an adequate appropriate sequential test where deemed necessary upfront as soon as you can. Really in my view this is actually
Speaker C: quite a good point that um, not all sites appear to be subject to a sequential test. The MPPF suggests every site should be, but not every local planning authority actually requests that right at the beginning. And there are plenty of examples where you either get challenged and you can get challenged by a whole host of different people, uh, and bodies. I mean in some cases it will be competitors. If you haven't submitted that sequential test right at the beginning, then say a supermarket may challenge another supermarket's application on the grounds that it's not been sequentially tested and the same for other developments. So it's getting an understanding at the beginning whether or not the local authority has say, a track record of applying sequential tests. That's quite handy and useful. But if they don't apply it, what's the risk that somebody else is going to come in at any stage through the planning process and demand that you've done one? And doing it retrospectively is quite a hard task.
Speaker A: So with that sort of approach, with that, do we have any project example that either of you both have been through as part of that?
Speaker D: We've been involved in quite a number of sequential tests, some of which I've done quite a few, a number for energy schemes where, as Chris touched on, the site has been located in an area of flood risk. And um, what we have done is then undertaken a sequential test. One of the overriding material considerations for that is proximity to the grid connection. So that was upfront and foremost the uh, driving factor that then defined our search area for which we would assess what would be reasonably available site of equivalent size in order to deliver the project. That then informed the sequential test which we identified a number of sites, a number of alternative reasonably available sites were discounted on other grounds, other environmental grounds and logistical grounds, which then steered us to the application site we were developing, which was fortunate, but we ran with it and that was approved via the inspector and later permission was granted and I'm now the understanding that that particular development is up and running.
Speaker C: There is, uh, another site, a residential site that I worked on a couple of times and we did the sequential test, but the area or the scheme was about 50% of the site was residential development with um, a care home access, et cetera. But the rest of it was going to be, um, given over as a public country park. But in this particular case, that country park area was subjected to pretty much every source of flooding, had fluvial surface water and there was a little bit of reservoir tucked in there as well for good measure. But if you sequentially test the whole red line boundary against other sites, it would fare very poor. And there was a point where we were considering the fact that we may have to take the country park out of the application because if you included it, the sequential test just on the drainage side of it would rule that site out, whereas all the development was located in the non risk areas. So then that was a sort of a hybrid approach where we agreed with the local authority, you know, the country park was an essential part of the scheme. But if the sequential test ruled it out, that was nonsense of the process. So there was an agreement that we would look at what was the risk of just the development bit and then against the whole red line area. And that was a bit more sensible, a bit more logical. And you know, that one has, has got approval now and is under construction.
Speaker D: I think that's the other good point I think we touched on there, Chris, is the challenge, because one of the other things, uh, that has been of interest is how the rhetoric behind the sequential test is applied. So different local authorities and different officers interpret the sequential test and writing slightly differently. So as you mentioned there, like some will adopt a sequential approach to locating development within a red line boundary in a site and approve that where others can be a bit more, add a bit more scrutiny and won't accept that approach. So I think one of the other challenges that I've experienced is how it is being applied and viewed at a authority level. And that sort of creates some ambiguity on top of the ambiguity we've already mentioned within the text itself. So I think half of it would be getting a consistent approach from the local authorities on how they wish to see applied. And, um, that could only be supported by strengthening of the MPPF and the text within it and the associated guidance and local policies.
Speaker C: So off sort of the back of that, I mean, everybody kind of knows that the MPPF is up for review and modification at the moment. But also fairly recently there was additional guidance sent out to local planning authorities from DEFRA Environment Agency that actually did have a sort of caveat in there, which was along the lines of if your development has allocated areas of flood risk for open space, biodiversity net, gain public immunity, that is not built development that you may not need to do the sequential test. So that one is kind of rippling through, although, because we've got the MPPF and then we've got the policy practice guidance that goes with it, and then we've got these standing, uh, advice notes. They've all got different levels of legal standing. So what we're waiting for is to see that if that kind of statement can get rippled back into the mppf, that would be handy for a lot of developers and make the sequential test functionable.
Speaker A: So Neela, during the conversation that we have had during this podcast, it's that we've discussed the best approaches and obviously your takeaways from what's been going on with previous projects or case law that is emerged. Stay informed about emerging guidance along with the NPPF framework bringing to it and the update that's going to come to you for it. Would there be any other sort of top highlights that we may have already discussed and sort of gone into detail? But as before, you go into the sequential test, what would be the hard hitting points that you would do beforehand?
Speaker C: Make sure there's collaboration going on and that, and that you're not losing or deferring the preparation of the test between different disciplines, getting the definition of the project right so that everybody agrees what it is and uh, what, you know, as Jonathan said about grid connections, or maybe you've got a medical center or something, something that's unique, potentially unique, that defines your project and that defines the search area. Agree that search area, then it becomes kind of a two part assessment. From our point of view as flood risk engineers, we would look at comparing that site to all of the other potential alternatives and then you might end up with a big long list of 200 sites or whatever. And you come, I don't know, 12th in that big long list. And then as we said earlier about is it reasonable to include all of that 200? And then you look at, maybe the size doesn't work, in which case you know, the list then goes down to 50 perhaps. And then you look at other things such as your uniqueness and then that might rule out a few others. And then it's really over to the planners and the clients to then look at, uh, what sites remain and then do the assessment of what's available, what's reasonably available, and then that gets you down to that really short list of the sequentially preferable or not sites. So as long as it's done rigorously and in the methodology of the sequential test with case law behind it, then that's where you really need to go.
Speaker D: For my input, I would say I would be mindful of the sequential tests at the due diligence stage. If you're looking at a new site, be mindful that if you uh, are looking at a site that this may need to be applied and an awareness that you don't want to get down the track and find that you still need to apply this. And at that point when you've invested a significant amount of funds into developing a concept of the site layout and everything else that you need to undertake the sequential test. And um, at that point you establish that there is in fact a reasonably available site and you could effectively be challenged upon it. So that initial awareness, I would say as part of this podcast, we're aware that the sequential test is becoming more of a hot topic, then the scrutiny being applied to it is at the forefront. So for any developers moving forward with the site, as I say, an awareness that this test may be required and having that ready is I think the best advice.
Speaker C: We have heard of cases where nobody did a sequential test and it wasn't until the site went to appeal that the inspector raised the question himself. And that is really sort of last minute.
Speaker D: And at that stage just adding to Chris's air, it can cause lots of procedural issues whether you can, you can actually apply new information such as sequential tests to the application or whether at that point, depending on the type of application, the whole things needs to be withdrawn and then started all over again, which you could probably appreciate is significantly costly.
Speaker A: So I suppose we're nearing the end of uh, today's podcast, but I do want to highlight that as well as this podcast, you both had actually partaken in a webinar as well that's also available where you've probably gone into a bit more detail than the time that we've got today.
Speaker C: Yeah, it's part of the um, RPS Leading Minds program that was at the beginning of October, so I think there'll probably be a link available.
Speaker A: There were a few questions near the end of that webinar that came out where there's quite a few interesting answers which I think would probably add to this podcast. So one of the questions that we had was have you encountered instances where climate change modeling necessitated a redefinition of flood zones specifically for floods? I want in this one, as requested by the Environment Agency for a particular site.
Speaker C: Yes, this does crop up because, uh, a developer, as Jonathan said, spends an awful lot of money looking at the master planning and site layout and they may well commission a flood model to be done because there's some dubiousness about the mapping that goes behind it and they might end up uh, redefining floodplains, uh, within their red line area or maybe the locality of it. The issue with the sequential test is that uh, you don't have the ability to do that with all of the other 200 sites. There has to be a methodology that is the same for every site. So unless the local authorities agreed otherwise, I think you've got to look at the available mapping of the flood zones, the available mapping of the surface water zones and all those and compare every single site the same way. Then it's a, it's a true comparison. And only then can you start looking in the same way as the uniqueness of the site. You can then look at uh, well actually, even though it's come I, uh, know, 15th in the list, you've actually got you know, a different flood zone. And if you looked at the flood zone differently, and we have done this on a couple of occasions, we've looked at it differently, you then have another entry in that league table and you may be ninth because your flood zones have been redefined. So then you present that data as well.
Speaker D: It can come a bit of a challenge as well because um, the local plans are normally defined or assessed against a strategic risk assessment within which the local authority may have done some site local specific hydraulic modelling which is normally focused on urban areas where they're looking to develop in large accommodations. When if you're looking at say a, uh, residential development which is further out in a more urbanised area, that modeling is pretty sparse and may not have been undertaken. Which there uh, as Chris says, leads you a bit of a challenge between what information do you have available and what are you comparing against what reasonably available sites and the modeling information that you have. So that's another challenge which we've got to overcome in the sequential test.
Speaker A: And another question that we had from the webinar was does the sequential test potentially contribute to viable development sites remaining unused due to other locations being deemed more favorable from a flood risk perspective?
Speaker C: Absolutely. I'm sure that there are many occasions where you can look at a site and if you're applying the sequential test in a black and white sort of manner, then it will present with a, um, site that's logically sensible to develop, not being developed because the sequential test is not. But hopefully local plans and local planning policies would have measures that would overcome that.
Speaker D: Yeah, I think it'd be also supported by, as we, as we mentioned earlier in the podcast, that the other material factors which underpinned the site allocation and um, what's reasonable. So if there are other considerations such as, as we mentioned, transportation, local amenities, all the rest of it, which would potentially beyond hydrology and flood risk, bum those sites up, then they should be deemed seemed as viable if the evidence supports it.
Speaker A: And the final question that we've got, kind of a double question, so the first half would be, should greater emphasis be placed on a sequential approach to development within site boundaries as a key factor in effective spatial planning. And the second part, given the need to promote development to meet national targets, is there a risk that sequential test is being used to obstruct rather than facilitate development?
Speaker C: We've probably touched on both of those with the elements of designing sequentially within the red line boundary, which most master plans, if not all master plans, should be doing. Uh, and should be looking at. Uh, and maybe the MPPF doesn't really emphasize that enough at the moment that that's what should be happening. The second point we've also sort of mentioned about abstracting applications by objecting to, um, the sequential test being undertaken or not undertaken or not covering a certain flood risk aspect that's certainly come up. And maybe in cases local planning authorities have a list of objections to a particular site, it's another thing that can be added to that list of objections to give it some more weight. So there's planning, so there's a lot of give and take and, um, competing issues that need to be weighed up.
Speaker A: Well, we reached the end of the podcast for today, but I'd like to thank you both for your time.
Speaker C: Thank you, thank you.
Speaker B: The Building Sustainably Podcast is brought to you by rps. To find out more about RPS and how we can help you deliver future ready development, visit rpsgroup.com and then search for the Building Sustainably Podcast in Apple Podcasts, Spotify, and wherever else you get your podcasts. Make sure to click subscribe so you don't miss any future episodes. On behalf of the team here at rps, thanks for listening.